1. | Obtain docking points and bushings from detachable docking hardware kit for Tour-Pak. Discard screws. | |||||||||||||
2. | See Figure 6. Place a bushing (A) into each of the fender support (B) holes. The beveled side of the bushings ( Figure 5 , Item 1) face out from the fender. | |||||||||||||
3. | Install front and rear docking points (C, D). For each docking point, place the countersunk side of docking point so it engages bushing ( Figure 5 , Item 2). |
Figure 1. Existing Hardware (With Docking Points)
Figure 2. Existing Hardware (Without Docking Points) | ||||||||||||
4. | Place docking point (1) on top of (outside) front and rear docking points (C, D). The countersunk side of the outboard docking point mates against inboard docking point ( Figure 5 ). NOTE Make sure Loctite 243 (blue) is applied to docking point screws. Failure to do so may cause the docking points and accessory to become loose on motorcycle. | |||||||||||||
5. | Apply Loctite 243 (blue) to last four threads of docking point screws (2). | |||||||||||||
6. | Thread screws (2) through docking points, front and rear docking points, bushings, and into fender and bracket (behind fender). Tighten screws to 21-27 ft-lbs (28-37 Nm). | |||||||||||||
7. | If detachable saddlebags have been installed, install docking point (1) from kit to saddlebag lower front support with screw (3), spacers (E, F) and lockwasher (H). If installing saddlebag kit for the first time, refer to the instruction sheet for that kit to install lower front support. Discard the mini-docking point from the saddlebag kit and replace with the docking point from this kit. | |||||||||||||
8. | Repeat steps for opposite side. |
1 | Docking point |
2 | Passenger footpeg |
3 | Lower front support |
1 | Screw |
2 | Split lockwasher |
3 | Docking point |
4 | Spacer (small) |
5 | Spacer (large) |
6 | Lower front support |
1 | Beveled side of bushing |
2 | Countersunk end (faces fender support) |
3 | Docking point |
1. | Remove docking hardware (screws). | |
2. | Clean threadlocker residue off of screw threads. | |
3. | Apply Loctite 243 (blue) to last four threads of docking point screws. | |
4. | Install screws and tighten finger-tight. | |
5. | Rotate docking points clockwise approximately 45 degrees from their previous position. | |
6. | Tighten the docking hardware to 28–37 N·m (21–27 ft-lbs). | |
7. | Repeat as required, up to three adjustments. After the third adjustment, new docking points must be installed. |
Item | Description (Quantity) | Part Number |
---|---|---|
1 | Docking point (6) | 53683-96 |
2 | Screw, 3/8-16 x 2-3/4 in. (4) | Not Sold Separately |
3 | Screw, 5/16-18 x 2-1/2 in. Grade 8 (2) (Used for lower front docking point mounting) | 3584 |
Items not included in kit: | ||
A | Bushing (2) | Part of Docking Hardware Kit for Tour-Pak |
B | Fender support | |
C | Docking point, front | Part of Docking Hardware Kit for Tour-Pak |
D | Docking point, rear | Part of Docking Hardware Kit for Tour-Pak |
E | Spacer | Included in Saddlebag Kit |
F | Spacer | Included in Saddlebag Kit |
G | Saddlebag lower front support | Included in Saddlebag Kit |
H | Lockwasher | Included in Saddlebag Kit |